South Park Drive Improvement Project
The South Park Drive Improvement Project affects approximately 1.1 miles of roadway. The roadway to be improved is South Park Drive from Highway 13 to County Road 27. The proposed improvement is a full depth mill & overlay that includes installation of pedestrian crossings and median treatments. South Park Drive from Highway 13 to Louisiana Avenue would be converted to a 3-lane roadway. South Park Drive is a Municipal State Aid route, so Municipal State Aid Construction funds will constitute the primary funding source.
The South Park Drive Improvement Project affects approximately 1.1 miles of roadway. The roadway to be improved is South Park Drive from Highway 13 to County Road 27. The proposed improvement is a full depth mill & overlay that includes installation of pedestrian crossings and median treatments. South Park Drive from Highway 13 to Louisiana Avenue would be converted to a 3-lane roadway. South Park Drive is a Municipal State Aid route, so Municipal State Aid Construction funds will constitute the primary funding source.
-
July 21-25
Share July 21-25 on Facebook Share July 21-25 on Twitter Share July 21-25 on Linkedin Email July 21-25 linkHere are your construction updates for next week.
Monday, July 21st
- Crews will be working on concrete medians and raising of the utility covers for Phase 2 portion of the project (street segment from Quebec Avenue to Louisiana Avenue – roundabout)
Tuesday, July 22nd
- Paving of the second layer of bituminous pavement will take place for Phase 2. Phase 1 portion of the project (from Louisiana to County Road 27) will see minor work to prepare for paving of the second layer of bituminous pavement. The placement of the second layer of bituminous for Phase 1 is scheduled for Monday, July 28th.
Wednesday, July 23rd through Friday, July 25th
- Phase 2 portion of the project will see placement of topsoil and preparation for restoration of the impacted areas. Once topsoil placement is complete, the segment of South Park Drive from Quebec to Louisiana will be opened to traffic. Phase 3 portion of the project (Quebec to Highway 13) will continue with utility work.
-
July 10 - 15
Share July 10 - 15 on Facebook Share July 10 - 15 on Twitter Share July 10 - 15 on Linkedin Email July 10 - 15 linkConstruction Update: July 10 - 15
Phase I: (CR 27 to Louisiana Ave)
Yard restoration will continue.
Phase II (Louisiana Ave to East of Quebec Ave):
Thursday, 7/10 – Our crews will be paving the pedestrian trail.
Friday, 7/11 – We'll be placing concrete curb & gutter in the medians. In the event of rain on Friday, the work will be moved to Monday, 7/14 .
Tuesday, 7/15 – Reclaiming of the street will begin along with preparing for laying the first lift of asphalt.
Phase III (East of Quebec Ave to Hwy 13)
Tuesday, 7/15 – Work will begin in Phase III.
Tuesday, 7/15 – Small utilities and fire hydrants will be relocated in preparation for the road construction.
TEMPORARY ROAD CLOSURE: The Westbound lane will be temporarily closed from Quebec to Hwy 13. See map.
-
June 30 - July 4, 2025
Share June 30 - July 4, 2025 on Facebook Share June 30 - July 4, 2025 on Twitter Share June 30 - July 4, 2025 on Linkedin Email June 30 - July 4, 2025 linkPhase I - Trail construction
Phase II - Concrete driveway, curb & gutter and sidewalk placement
No work on Friday, July 4.
-
June 18 - 27, 2025
Share June 18 - 27, 2025 on Facebook Share June 18 - 27, 2025 on Twitter Share June 18 - 27, 2025 on Linkedin Email June 18 - 27, 2025 linkPhase I
- First lift of asphalt will be laid.
- Prepping & paving trails.
- Continue with irrigation repairs and yard grading.
Phase II
- REMINDER: Phase II begins.
- Begin removal of curb, gutter & sidewalks
-
June 16 - 23, 2025
Share June 16 - 23, 2025 on Facebook Share June 16 - 23, 2025 on Twitter Share June 16 - 23, 2025 on Linkedin Email June 16 - 23, 2025 linkMonday, June 16 - Reclaiming roadway in Phase I
Tuesday - Thursday - Subgrade prep for road & trails
Friday - Saturday - Subgrade Stabilization
Monday, June 23 - Paving of 1st lift of pavement in Phase I. Removals will begin in Phase II.
-
June 9 - 13, 2025
Share June 9 - 13, 2025 on Facebook Share June 9 - 13, 2025 on Twitter Share June 9 - 13, 2025 on Linkedin Email June 9 - 13, 2025 linkThank you for signing up on Let's Talk Savage for updates on the South Park Drive Project in your neighborhood.
Updates for the week of June 9 - 13, 2025:
- Storm sewer work and grading of pond.
- Begin irrigation repairs.
- Backfilling curb & gutter.
- Placing topsoil in medians.
- Prepping for trail and driveway repairs.
Thank you!
-
June 2 - June 6, 2025
Share June 2 - June 6, 2025 on Facebook Share June 2 - June 6, 2025 on Twitter Share June 2 - June 6, 2025 on Linkedin Email June 2 - June 6, 2025 link- Complete retaining wall.
- Begin installing concrete curb & gutter replacement.
- Begin storm sewer work in pond.
- Begin island construction.
-
May 26 - 30, 2025
Share May 26 - 30, 2025 on Facebook Share May 26 - 30, 2025 on Twitter Share May 26 - 30, 2025 on Linkedin Email May 26 - 30, 2025 link- Monday, May 26 no work. Observance of Memorial Day holiday.
- Continue with removals of sidewalk, curb & Gutter.
- Continue pond construction.
- Concrete replacement of curb & gutter and driveways.
-
May 19 - 23, 2025
Share May 19 - 23, 2025 on Facebook Share May 19 - 23, 2025 on Twitter Share May 19 - 23, 2025 on Linkedin Email May 19 - 23, 2025 linkContractor will continue with pond excavation, removal of sidewalk, bituminous pathways, and curb & gutter. Storm sewer installation will begin on Tuesday. Placement of curb & gutter and ADA pedestrian ramps on Friday. All depending on weather. Have a great week!
-
May 13, 2025
Share May 13, 2025 on Facebook Share May 13, 2025 on Twitter Share May 13, 2025 on Linkedin Email May 13, 2025 linkTree removal along Featherstone Lake is limited to only City Pond 29-3. The purpose of this work includes:
- Removing sediment
- Repairing City storm sewer
- Repairing eroding slopes
- Increasing water quality efficiency of the pond
05.01.25 Neighborhood Meeting Notice
Resident Brochure
01.08.25 Neighborhood Meeting Presentation