September 22 to September 29, 2025

Phase 3 (East of Quebec Ave to Hwy 13)

  • Monday, 9/22: The 2nd lift of asphalt will be completed.
  • Monday, 9/22 & Tuesday, 9/23: Restoration work will continue.
  • Wednesday, 9/24: The last lift of asphalt will be put down.
  • Friday, 9/26: South Park Drive will be open for driving.
  • Monday, 9/29: The road will be striped.

NOTE: This schedule is all weather dependent.

Questions? Please call John Wichman at 612-490-8744.