August 8, 2025
Phase 3 (East of Quebec Ave to Hwy 13)
- Crews will begin Storm Sewer work on Monday, August 12. This work will take approximately 2 weeks.
- Please be aware of traffic control changes beginning on Monday, August 12:
- Hwy 13 South Frontage Road to Quebec will be open to Eastbound traffic only for approximately 2 weeks.
- Once the Storm Sewer work is complete, Phase 3 will then be shut down completely for approximately another 2 weeks.
Questions? Please call John Wichman at 612-490-8744.
Thank you!