September 15 - 19, 2025

Phase 3 (East of Quebec Ave to Hwy 13)

  • Monday: Crews will be working on reclaiming the existing pavement.
  • Tuesday: Concrete placement will occur on sidewalk, pedestrian ramps and medians.
  • Wednesday: Paving of the base course will take place.
  • Thursday & Friday: Crews will be adjusting manholes and valve boxes. Restoration work will also begin.

Questions? Please call John Wichman at 612-490-8744.

Share September 15 - 19, 2025 on Facebook Share September 15 - 19, 2025 on Twitter Share September 15 - 19, 2025 on Linkedin Email September 15 - 19, 2025 link