September 15 - 19, 2025
Phase 3 (East of Quebec Ave to Hwy 13)
- Monday: Crews will be working on reclaiming the existing pavement.
- Tuesday: Concrete placement will occur on sidewalk, pedestrian ramps and medians.
- Wednesday: Paving of the base course will take place.
- Thursday & Friday: Crews will be adjusting manholes and valve boxes. Restoration work will also begin.
Questions? Please call John Wichman at 612-490-8744.