August 1, 2025
Phase 1 (Louisiana to CR 27) and Phase 2 (Quebec Ave to Louisiana Ave):
- Happy to report that Phase 1 and 2 are now open for traffic! The last lift of asphalt along with the median planting will take place this fall.
Phase 3:
- Crews will continue working on relocating small utilities through August 11.
Questions? Please call John Wichman at 612-490-8744.