August 1, 2025

Phase 1 (Louisiana to CR 27) and Phase 2 (Quebec Ave to Louisiana Ave):

  • Happy to report that Phase 1 and 2 are now open for traffic! The last lift of asphalt along with the median planting will take place this fall.

Phase 3:

  • Crews will continue working on relocating small utilities through August 11.

Questions? Please call John Wichman at 612-490-8744.

Share August 1, 2025 on Facebook Share August 1, 2025 on Twitter Share August 1, 2025 on Linkedin Email August 1, 2025 link

Consultation has concluded

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>