September 4 - 12, 2025

Phase 1 (Louisiana to CR 27) and Phase 2 (Quebec Ave to Louisiana Ave)

  • The wear course is complete. Striping, landscaping and streetlights still remain.

Phase 3 (East of Quebec Ave to Hwy 13)

  • Phase 3 will be completely closed from Quebec Avenue to Hwy 13 and Quebec Avenue to Primrose school. This closure will be in effect until the end of September.
  • Crews will continue to work on storm sewer throughout the week along with curb removal and replacement.
  • Trail is mostly complete and is expected to be 100% complete by the end of Saturday, September 6.
  • Curb and gutter installation will begin on the turn lanes and medians later next week.
  • Milling of the road will begin September 11 & 12.

Questions? Please call John Wichman at 612-490-8744.