September 4 - 12, 2025
Phase 1 (Louisiana to CR 27) and Phase 2 (Quebec Ave to Louisiana Ave)
- The wear course is complete. Striping, landscaping and streetlights still remain.
Phase 3 (East of Quebec Ave to Hwy 13)
- Phase 3 will be completely closed from Quebec Avenue to Hwy 13 and Quebec Avenue to Primrose school. This closure will be in effect until the end of September.
- Crews will continue to work on storm sewer throughout the week along with curb removal and replacement.
- Trail is mostly complete and is expected to be 100% complete by the end of Saturday, September 6.
- Curb and gutter installation will begin on the turn lanes and medians later next week.
- Milling of the road will begin September 11 & 12.
Questions? Please call John Wichman at 612-490-8744.
Share September 4 - 12, 2025 on Facebook
Share September 4 - 12, 2025 on Twitter
Share September 4 - 12, 2025 on Linkedin
Email September 4 - 12, 2025 link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends