South Park Drive Improvement Project

Share South Park Drive Improvement Project on Facebook Share South Park Drive Improvement Project on Twitter Share South Park Drive Improvement Project on Linkedin Email South Park Drive Improvement Project link

The South Park Drive Improvement Project affects approximately 1.1 miles of roadway. The roadway to be improved is South Park Drive from Highway 13 to County Road 27. The proposed improvement is a full depth mill & overlay that includes installation of pedestrian crossings and median treatments. South Park Drive from Highway 13 to Louisiana Avenue would be converted to a 3-lane roadway. South Park Drive is a Municipal State Aid route, so Municipal State Aid Construction funds will constitute the primary funding source.

The South Park Drive Improvement Project affects approximately 1.1 miles of roadway. The roadway to be improved is South Park Drive from Highway 13 to County Road 27. The proposed improvement is a full depth mill & overlay that includes installation of pedestrian crossings and median treatments. South Park Drive from Highway 13 to Louisiana Avenue would be converted to a 3-lane roadway. South Park Drive is a Municipal State Aid route, so Municipal State Aid Construction funds will constitute the primary funding source.

  • September 26, 2025

    Share September 26, 2025 on Facebook Share September 26, 2025 on Twitter Share September 26, 2025 on Linkedin Email September 26, 2025 link

    Very exciting news...South Park Drive will be opening today!! Traffic control removal will begin at 2:00 p.m.

    Thank you.

  • September 22 to September 29, 2025

    Share September 22 to September 29, 2025 on Facebook Share September 22 to September 29, 2025 on Twitter Share September 22 to September 29, 2025 on Linkedin Email September 22 to September 29, 2025 link

    Phase 3 (East of Quebec Ave to Hwy 13)

    • Monday, 9/22: The 2nd lift of asphalt will be completed.
    • Monday, 9/22 & Tuesday, 9/23: Restoration work will continue.
    • Wednesday, 9/24: The last lift of asphalt will be put down.
    • Friday, 9/26: South Park Drive will be open for driving.
    • Monday, 9/29: The road will be striped.

    NOTE: This schedule is all weather dependent.

    Questions? Please call John Wichman at 612-490-8744.

  • September 15 - 19, 2025

    Share September 15 - 19, 2025 on Facebook Share September 15 - 19, 2025 on Twitter Share September 15 - 19, 2025 on Linkedin Email September 15 - 19, 2025 link

    Phase 3 (East of Quebec Ave to Hwy 13)

    • Monday: Crews will be working on reclaiming the existing pavement.
    • Tuesday: Concrete placement will occur on sidewalk, pedestrian ramps and medians.
    • Wednesday: Paving of the base course will take place.
    • Thursday & Friday: Crews will be adjusting manholes and valve boxes. Restoration work will also begin.

    Questions? Please call John Wichman at 612-490-8744.

  • September 4 - 12, 2025

    Share September 4 - 12, 2025 on Facebook Share September 4 - 12, 2025 on Twitter Share September 4 - 12, 2025 on Linkedin Email September 4 - 12, 2025 link

    Phase 1 (Louisiana to CR 27) and Phase 2 (Quebec Ave to Louisiana Ave)

    • The wear course is complete. Striping, landscaping and streetlights still remain.

    Phase 3 (East of Quebec Ave to Hwy 13)

    • Phase 3 will be completely closed from Quebec Avenue to Hwy 13 and Quebec Avenue to Primrose school. This closure will be in effect until the end of September.
    • Crews will continue to work on storm sewer throughout the week along with curb removal and replacement.
    • Trail is mostly complete and is expected to be 100% complete by the end of Saturday, September 6.
    • Curb and gutter installation will begin on the turn lanes and medians later next week.
    • Milling of the road will begin September 11 & 12.

    Questions? Please call John Wichman at 612-490-8744.

  • August 25 - September 2

    Share August 25 - September 2 on Facebook Share August 25 - September 2 on Twitter Share August 25 - September 2 on Linkedin Email August 25 - September 2 link

    Phase 1 (Louisiana to CR 27) and Phase 2 (Quebec Ave to Louisiana Ave)

    • The wear course is complete. Striping, landscaping and streetlights still remain.

    Phase 3 (East of Quebec Ave to Hwy 13)

    • Crews will continue to work on storm sewer throughout the week along with curb removal and replacement.
    • The trail will be graded, and rock will be laid down. We expect the trail to be paved on Friday, August 29.

    September 2

    • Phase 3 will be completely closed from Quebec Avenue to Hwy 13 and Quebec Avenue to Primrose school. This closure will be in effect until the end of September.
  • August 15 - 22, 2025

    Share August 15 - 22, 2025 on Facebook Share August 15 - 22, 2025 on Twitter Share August 15 - 22, 2025 on Linkedin Email August 15 - 22, 2025 link

    Phase 1 (Louisiana to CR 27) and Phase 2 (Quebec Ave to Louisiana Ave)

    • Crews will be working on landscaping the median with hydroseeding, plants and trees on Wednesday.
    • The final lift of asphalt will be laid down on Friday, August 22 weather permitting.

    Phase 3 (East of Quebec Ave to Hwy 13)

    • Storm sewer work will continue.
    • The removal of curb, gutter, sidewalks and driveways will be worked all week.

    The Louisiana Avenue & South Park Drive roundabout will be closed to traffic during the early hours of Friday, August 22 and Monday, August 25 from 4:00 a.m. to 6:00 a.m. to complete milling and paving of the roundabout.

    QUESTIONS? Please contact John Wichman at 612-890-8744.

    Thank you!

  • Revised August 8, 2025

    Share Revised August 8, 2025 on Facebook Share Revised August 8, 2025 on Twitter Share Revised August 8, 2025 on Linkedin Email Revised August 8, 2025 link

    We have received an update to the traffic control information that was sent out earlier today.

    • Phase 3 (East of Quebec Ave to Hwy 13)
      • Revised: Please be aware of traffic control changes beginning on Tuesday, August 12 (not Monday as previously stated):
        • Hwy 13 South Frontage Road to Quebec will be open to Eastbound traffic only through August 17.
        • Phase 3 will be shut down completely beginning August 18 until further notice. Watch for further updates as to when it may open.
  • August 8, 2025

    Share August 8, 2025 on Facebook Share August 8, 2025 on Twitter Share August 8, 2025 on Linkedin Email August 8, 2025 link

    Phase 3 (East of Quebec Ave to Hwy 13)

    • Crews will begin Storm Sewer work on Monday, August 12. This work will take approximately 2 weeks.
    • Please be aware of traffic control changes beginning on Monday, August 12:
      • Hwy 13 South Frontage Road to Quebec will be open to Eastbound traffic only for approximately 2 weeks.
    • Once the Storm Sewer work is complete, Phase 3 will then be shut down completely for approximately another 2 weeks.

    Questions? Please call John Wichman at 612-490-8744.

    Thank you!

  • August 1, 2025

    Share August 1, 2025 on Facebook Share August 1, 2025 on Twitter Share August 1, 2025 on Linkedin Email August 1, 2025 link

    Phase 1 (Louisiana to CR 27) and Phase 2 (Quebec Ave to Louisiana Ave):

    • Happy to report that Phase 1 and 2 are now open for traffic! The last lift of asphalt along with the median planting will take place this fall.

    Phase 3:

    • Crews will continue working on relocating small utilities through August 11.

    Questions? Please call John Wichman at 612-490-8744.

  • July 28 Construction Update

    Share July 28 Construction Update on Facebook Share July 28 Construction Update on Twitter Share July 28 Construction Update on Linkedin Email July 28 Construction Update link

    Monday & Tuesday

    • Restoration will begin in boulevards and yards in Phase 1 (Louisiana to CR 27) and Phase 2 (Quebec Ave to Louisiana Ave) in preparation for opening up this area to traffic soon.

    Wednesday

    • Installation of the 2nd lift of asphalt will take place in Phase 1.

    We are having an unexpected delay in Phase 3 due to issues in relocating small utilities. This work will continue until August 11.

    Questions? Please call John Wichman at 612-490-8744.

    Thank you.

Page last updated: 26 Sep 2025, 09:09 AM