- Complete retaining wall.
- Begin installing concrete curb & gutter replacement.
- Begin storm sewer work in pond.
- Begin island construction.
Share May 26 - 30, 2025 on Facebook
Share May 26 - 30, 2025 on Linkedin
Email May 26 - 30, 2025 link
- Monday, May 26 no work. Observance of Memorial Day holiday.
- Continue with removals of sidewalk, curb & Gutter.
- Continue pond construction.
- Concrete replacement of curb & gutter and driveways.
Share May 19 - 23, 2025 on Facebook
Share May 19 - 23, 2025 on Linkedin
Email May 19 - 23, 2025 link
Contractor will continue with pond excavation, removal of sidewalk, bituminous pathways, and curb & gutter. Storm sewer installation will begin on Tuesday. Placement of curb & gutter and ADA pedestrian ramps on Friday. All depending on weather. Have a great week!
Share May 13, 2025 on Facebook
Share May 13, 2025 on Linkedin
Email May 13, 2025 link
Tree removal along Featherstone Lake is limited to only City Pond 29-3. The purpose of this work includes:
- Removing sediment
- Repairing City storm sewer
- Repairing eroding slopes
- Increasing water quality efficiency of the pond
Share May 12 - 16, 2025 on Facebook
Share May 12 - 16, 2025 on Linkedin
Email May 12 - 16, 2025 link
Phase I
- Road Closures and Detours. See map.
- Installing traffic control signage.
- Installing erosion control inlet protection.
- Clearing and grubbing trees around pond.
- Repairing sanitary sewer.
Share May 1, 2025 on Facebook
Share May 1, 2025 on Linkedin
Email May 1, 2025 link
Thank you for signing up for Let's Talk Savage! Construction for South Park Drive is scheduled to begin on Monday, May 12, 2025. Construction updates will be provided weekly!