July 10 - 15

Construction Update: July 10 - 15

Phase I: (CR 27 to Louisiana Ave)

Yard restoration will continue.

Phase II (Louisiana Ave to East of Quebec Ave):

Thursday, 7/10 – Our crews will be paving the pedestrian trail.

Friday, 7/11 – We'll be placing concrete curb & gutter in the medians. In the event of rain on Friday, the work will be moved to Monday, 7/14 .

Tuesday, 7/15 – Reclaiming of the street will begin along with preparing for laying the first lift of asphalt.

Phase III (East of Quebec Ave to Hwy 13)

Tuesday, 7/15 – Work will begin in Phase III.

Tuesday, 7/15 – Small utilities and fire hydrants will be relocated in preparation for the road construction.

TEMPORARY ROAD CLOSURE: The Westbound lane will be temporarily closed from Quebec to Hwy 13. See map.