July 10 - 15
Construction Update: July 10 - 15
Phase I: (CR 27 to Louisiana Ave)
Yard restoration will continue.
Phase II (Louisiana Ave to East of Quebec Ave):
Thursday, 7/10 – Our crews will be paving the pedestrian trail.
Friday, 7/11 – We'll be placing concrete curb & gutter in the medians. In the event of rain on Friday, the work will be moved to Monday, 7/14 .
Tuesday, 7/15 – Reclaiming of the street will begin along with preparing for laying the first lift of asphalt.
Phase III (East of Quebec Ave to Hwy 13)
Tuesday, 7/15 – Work will begin in Phase III.
Tuesday, 7/15 – Small utilities and fire hydrants will be relocated in preparation for the road construction.
TEMPORARY ROAD CLOSURE: The Westbound lane will be temporarily closed from Quebec to Hwy 13. See map.