2026 Street Improvement Project

Share 2026 Street Improvement Project on Facebook Share 2026 Street Improvement Project on Twitter Share 2026 Street Improvement Project on Linkedin Email 2026 Street Improvement Project link

The City Council has ordered the preparation of a feasibility report for the streets proposed to be improved in 2026. Below is a map showing the streets that will be evaluated for inclusion in the 2026 Street Improvement Project. Streets may be added or removed depending on the available budget.

The City Council has ordered the preparation of a feasibility report for the streets proposed to be improved in 2026. Below is a map showing the streets that will be evaluated for inclusion in the 2026 Street Improvement Project. Streets may be added or removed depending on the available budget.

  • Construction Update Week of 5/4

    Share Construction Update Week of 5/4 on Facebook Share Construction Update Week of 5/4 on Twitter Share Construction Update Week of 5/4 on Linkedin Email Construction Update Week of 5/4 link

    Thank you for signing up on Let's Talk Savage for updates on the 2026 Street Improvement Project in your neighborhood.

    Week of May 4, 2026

    • Phase 1:
      • Crews will be replacing bolts on the gate valves that are part of the water main. They will start on Colorado Avenue and will work to the east.
      • New Storm Sewer installation will begin on Colorado Avenue and will work to the east.
      • Concrete sidewalk panels will be removed Tuesday or Wednesday at the intersections of 140th Street. Crews will be removing dirt and placing new gravel in preparation for new pedestrian ramps that will be installed in a few weeks.
    • Phase 1 & 2:
      • Please continue getting your mail in the temporary mailboxes located on Connelly Parkway.
      • Expect some heavy equipment and trenching which may cause minor delays.

    This information is general project information. If you have specific questions regarding the impacts to your property, please contact us directly.

    Questions? Please call Craig Svoboda at 612-490-8748.

    Thank you for signing up on Let's Talk Savage for updates on the 2026 Street Improvement Project in your neighborhood.

    Week of May 4, 2026

    • Phase 1:
      • Crews will be replacing bolts on the gate valves that are part of the water main. They will start on Colorado Avenue and will work to the east.
      • New Storm Sewer installation will begin on Colorado Avenue and will work to the east.
      • Concrete sidewalk panels will be removed Tuesday or Wednesday at the intersections of 140th Street. Crews will be removing dirt and placing new gravel in preparation for new pedestrian ramps that will be installed in a few weeks.
    • Phase 1 & 2:
      • Please continue getting your mail in the temporary mailboxes located on Connelly Parkway.
      • Expect some heavy equipment and trenching which may cause minor delays.

    This information is general project information. If you have specific questions regarding the impacts to your property, please contact us directly.

    Questions? Please call Craig Svoboda at 612-490-8748.

  • Construction Update 4/27/26

    Share Construction Update 4/27/26 on Facebook Share Construction Update 4/27/26 on Twitter Share Construction Update 4/27/26 on Linkedin Email Construction Update 4/27/26 link
    • Crews will begin tree cutting Monday, 4/27/26 and will be done Wednesday, 4/29/26.
    • Pipe crews will start in Phase 1.
    • Xcel will be removing streetlights in Phases 1 & 2 in preparation for installing new storm sewer. They will be replaced when work is complete.
    • Crews will begin tree cutting Monday, 4/27/26 and will be done Wednesday, 4/29/26.
    • Pipe crews will start in Phase 1.
    • Xcel will be removing streetlights in Phases 1 & 2 in preparation for installing new storm sewer. They will be replaced when work is complete.
  • Construction Update 4/17/26

    Share Construction Update 4/17/26 on Facebook Share Construction Update 4/17/26 on Twitter Share Construction Update 4/17/26 on Linkedin Email Construction Update 4/17/26 link

    Construction Update

    Thank you for signing up on Let's Talk Savage for updates on the 2026 Street Improvement Project in your neighborhood.

    Here's what is happening next week:

    April 17, 2026

    McNamara Contracting will be onsite next week preparing for construction which will begin on Monday, April 27.

    • Crews will be installing inlet protection devices in the catch basins.
    • Saw cutting of marked curbs & sidewalks will begin.

    We look forward to working with you this summer. Construction schedules can be tricky at times, not to mention the weather, but we will do our best to communicate timely.

    Questions? Please call Craig Svoboda at 612-490-8748.

    Kind regards,

    The Project Team

    Construction Update

    Thank you for signing up on Let's Talk Savage for updates on the 2026 Street Improvement Project in your neighborhood.

    Here's what is happening next week:

    April 17, 2026

    McNamara Contracting will be onsite next week preparing for construction which will begin on Monday, April 27.

    • Crews will be installing inlet protection devices in the catch basins.
    • Saw cutting of marked curbs & sidewalks will begin.

    We look forward to working with you this summer. Construction schedules can be tricky at times, not to mention the weather, but we will do our best to communicate timely.

    Questions? Please call Craig Svoboda at 612-490-8748.

    Kind regards,

    The Project Team

Page last updated: 01 May 2026, 01:36 PM