2026 Street Improvement Project

Share 2026 Street Improvement Project on Facebook Share 2026 Street Improvement Project on X (formerly Twitter) Share 2026 Street Improvement Project on Linkedin Email 2026 Street Improvement Project link

The City Council has ordered the preparation of a feasibility report for the streets proposed to be improved in 2026. Below is a map showing the streets that will be evaluated for inclusion in the 2026 Street Improvement Project. Streets may be added or removed depending on the available budget.

The City Council has ordered the preparation of a feasibility report for the streets proposed to be improved in 2026. Below is a map showing the streets that will be evaluated for inclusion in the 2026 Street Improvement Project. Streets may be added or removed depending on the available budget.

  • Construction Update for the week of 7/6

    Share Construction Update for the week of 7/6 on Facebook Share Construction Update for the week of 7/6 on X (formerly Twitter) Share Construction Update for the week of 7/6 on Linkedin Email Construction Update for the week of 7/6 link

    Phase 3 & 4 (Preserve Trail)

    A few more changes for this week:
    • Wednesday, 7/1: No paving took place due to the weather.
    • Thursday, 7/2: Crews will finish paving.
    • Friday, 7/3: Holiday. Crews will not be working.

    Week of 7/6:

    You will still be able to get in and out of your home, but please expect minor delays and please no street parking on paving day. Our crew will help coordinate your access and get you in and out as quickly as possible. The second layer of asphalt will be installed at a later date.

    Questions? Please call Craig Svoboda at 612-490-8748.

    Thank you!

    Phase 3 & 4 (Preserve Trail)

    A few more changes for this week:
    • Wednesday, 7/1: No paving took place due to the weather.
    • Thursday, 7/2: Crews will finish paving.
    • Friday, 7/3: Holiday. Crews will not be working.

    Week of 7/6:

    You will still be able to get in and out of your home, but please expect minor delays and please no street parking on paving day. Our crew will help coordinate your access and get you in and out as quickly as possible. The second layer of asphalt will be installed at a later date.

    Questions? Please call Craig Svoboda at 612-490-8748.

    Thank you!

  • Construction Update / Paving

    Share Construction Update / Paving on Facebook Share Construction Update / Paving on X (formerly Twitter) Share Construction Update / Paving on Linkedin Email Construction Update / Paving link

    Phase 3 & 4 (Preserve Trail)

    We have a change in the paving schedule:
    • Tuesday, 6/30: Asphalt will be installed in all three of the cul-de-sacs (Preserve Place, Preserve Circle and Preserve Alcove).
    • Wednesday, 7/1: Preserve Trail will be paved. Weather depending.

    You will still be able to get in and out of your home, but please expect minor delays and please no street parking on paving day. Our crew will help coordinate your access and get you in and out as quickly as possible. The second layer of asphalt will be installed at a later date.

    • Thursday, 7/2: Crews will be backfilling curbs to get ready for restoration.
    • Friday, 7/3: Holiday. Crews will not be working.

    Phase 3 & 4 (Preserve Trail)

    We have a change in the paving schedule:
    • Tuesday, 6/30: Asphalt will be installed in all three of the cul-de-sacs (Preserve Place, Preserve Circle and Preserve Alcove).
    • Wednesday, 7/1: Preserve Trail will be paved. Weather depending.

    You will still be able to get in and out of your home, but please expect minor delays and please no street parking on paving day. Our crew will help coordinate your access and get you in and out as quickly as possible. The second layer of asphalt will be installed at a later date.

    • Thursday, 7/2: Crews will be backfilling curbs to get ready for restoration.
    • Friday, 7/3: Holiday. Crews will not be working.
  • Construction Update the Week of June 29

    Share Construction Update the Week of June 29 on Facebook Share Construction Update the Week of June 29 on X (formerly Twitter) Share Construction Update the Week of June 29 on Linkedin Email Construction Update the Week of June 29 link
    • Phase 3 & 4 (Preserve Trail)

      • Saturday (6/27) - Tuesday (6/30): Crews will be raising manhole covers & gate valve boxes and grating the aggregate base to prepare for paving.
      • Wednesday: The first of two layers of asphalt will be installed. You will still be able to get in and out of your home, but please expect minor delays and please no street parking on paving day. Our crew will help coordinate your access and get you in and out as quickly as possible. The second layer of asphalt will be installed at a later date.
      • Thursday: Crews will be backfilling curbs to get ready for restoration.
      • Friday: Holiday - no work.

    Irrigation Damage from Contruction? Please contact Sue with your address @ 952-882-2671 or smeyer@savagemn.gov(External link)(External link)(External link)(External link)(External link).

    Note: This information is general project information. If you have specific questions regarding the impacts to your property, please contact Craig directly. Phasing areas are specified on the construction brochure.

    Questions? Please call Craig Svoboda at 612-490-8748.

    Thank you for your patience!

    • Phase 3 & 4 (Preserve Trail)

      • Saturday (6/27) - Tuesday (6/30): Crews will be raising manhole covers & gate valve boxes and grating the aggregate base to prepare for paving.
      • Wednesday: The first of two layers of asphalt will be installed. You will still be able to get in and out of your home, but please expect minor delays and please no street parking on paving day. Our crew will help coordinate your access and get you in and out as quickly as possible. The second layer of asphalt will be installed at a later date.
      • Thursday: Crews will be backfilling curbs to get ready for restoration.
      • Friday: Holiday - no work.

    Irrigation Damage from Contruction? Please contact Sue with your address @ 952-882-2671 or smeyer@savagemn.gov(External link)(External link)(External link)(External link)(External link).

    Note: This information is general project information. If you have specific questions regarding the impacts to your property, please contact Craig directly. Phasing areas are specified on the construction brochure.

    Questions? Please call Craig Svoboda at 612-490-8748.

    Thank you for your patience!

  • Construction Update for Week of June 22

    Share Construction Update for Week of June 22 on Facebook Share Construction Update for Week of June 22 on X (formerly Twitter) Share Construction Update for Week of June 22 on Linkedin Email Construction Update for Week of June 22 link
    • Phase 3 & 4 (Preserve Trail)

      • Monday & Tuesday: Crews will continue installing new curb & gutter, sidewalks and pedestrian ramps.
      • Wednesday, Thursday & Friday: Milling and reclaiming will begin. Large equipment is needed for this process so please drive carefully and allow for a little extra time for minor delays.


    Note: This information is general project information. If you have specific questions regarding the impacts to your property, please contact Craig directly. Phasing areas are specified on the construction brochure.
    Questions? Please call Craig Svoboda at 612-490-8748.


    Thank you for your patience!

    • Phase 3 & 4 (Preserve Trail)

      • Monday & Tuesday: Crews will continue installing new curb & gutter, sidewalks and pedestrian ramps.
      • Wednesday, Thursday & Friday: Milling and reclaiming will begin. Large equipment is needed for this process so please drive carefully and allow for a little extra time for minor delays.


    Note: This information is general project information. If you have specific questions regarding the impacts to your property, please contact Craig directly. Phasing areas are specified on the construction brochure.
    Questions? Please call Craig Svoboda at 612-490-8748.


    Thank you for your patience!

  • Construction Update June 17, 2026

    Share Construction Update June 17, 2026 on Facebook Share Construction Update June 17, 2026 on X (formerly Twitter) Share Construction Update June 17, 2026 on Linkedin Email Construction Update June 17, 2026 link

    Phase 3 & 4 (Preserve Trail)

    • Due to the rain today (Wednesday, 6/17), the new curb & gutter, sidewalks and pedestrian ramps will be completed Thursday, Friday & Monday.

    Phase 3 & 4 (Preserve Trail)

    • Due to the rain today (Wednesday, 6/17), the new curb & gutter, sidewalks and pedestrian ramps will be completed Thursday, Friday & Monday.
  • Construction Update Week of June 15

    Share Construction Update Week of June 15 on Facebook Share Construction Update Week of June 15 on X (formerly Twitter) Share Construction Update Week of June 15 on Linkedin Email Construction Update Week of June 15 link


    • Phase 1 & 2

      • Monday & Tuesday: Crews will be finishing up sod placement. Please watch for a letter which was mailed out on June 11th regarding sod warranty and sod care. A copy of the letter has been saved under documents for your reference.
      • Mailboxes will be re-installed the beginning of the week.

    • If you have irrigation damage from construction, please contact Sue with your address @ 952-882-2671 or smeyer@savagemn.gov(External link)(External link)(External link)(External link)(External link).


      Phase 3 & 4 (Preserve Trail)

      • Monday & Tuesday: Crews will be removing marked curb & gutter along with grading in preparation for the new pedestrian ramps.
      • Wednesday, Thursday & Friday: New curb & gutter, sidewalks and pedestrian ramps will be placed.


    Note: This information is general project information. If you have specific questions regarding the impacts to your property, please contact Craig directly. Phasing areas are specified on the construction brochure.
    Questions? Please call Craig Svoboda at 612-490-8748.


    Thank you for your patience!




    • Phase 1 & 2

      • Monday & Tuesday: Crews will be finishing up sod placement. Please watch for a letter which was mailed out on June 11th regarding sod warranty and sod care. A copy of the letter has been saved under documents for your reference.
      • Mailboxes will be re-installed the beginning of the week.

    • If you have irrigation damage from construction, please contact Sue with your address @ 952-882-2671 or smeyer@savagemn.gov(External link)(External link)(External link)(External link)(External link).


      Phase 3 & 4 (Preserve Trail)

      • Monday & Tuesday: Crews will be removing marked curb & gutter along with grading in preparation for the new pedestrian ramps.
      • Wednesday, Thursday & Friday: New curb & gutter, sidewalks and pedestrian ramps will be placed.


    Note: This information is general project information. If you have specific questions regarding the impacts to your property, please contact Craig directly. Phasing areas are specified on the construction brochure.
    Questions? Please call Craig Svoboda at 612-490-8748.


    Thank you for your patience!



  • Construction Update Week of June 8

    Share Construction Update Week of June 8 on Facebook Share Construction Update Week of June 8 on X (formerly Twitter) Share Construction Update Week of June 8 on Linkedin Email Construction Update Week of June 8 link


    • Phase 1 & 2

      • All week: Restoration crews will start placing topsoil in boulevards in preparation for sod. Sod to follow soon! Watch for a mailing to be sent soon after sod is placed regarding sod care and warranty information.
      • Wednesday - Friday: Pond excavation work will begin.

    • If you have irrigation damage from construction, please contact Sue with your address @ 952-882-2671 or smeyer@savagemn.gov(External link)(External link)(External link)(External link).


      Phase 3 & 4 (Preserve Trail)

      • Utility work will begin.
      • Marked curb will be removed.
      • Old pedestrian ramps will be removed, and grading will take place in preparation for the new ramps.

    • Note: This information is general project information. If you have specific questions regarding the impacts to your property, please contact Craig directly. Phasing areas are specified on the construction brochure.

      Questions? Please call Craig Svoboda at 612-490-8748.

      Thank you for your patience!




    • Phase 1 & 2

      • All week: Restoration crews will start placing topsoil in boulevards in preparation for sod. Sod to follow soon! Watch for a mailing to be sent soon after sod is placed regarding sod care and warranty information.
      • Wednesday - Friday: Pond excavation work will begin.

    • If you have irrigation damage from construction, please contact Sue with your address @ 952-882-2671 or smeyer@savagemn.gov(External link)(External link)(External link)(External link).


      Phase 3 & 4 (Preserve Trail)

      • Utility work will begin.
      • Marked curb will be removed.
      • Old pedestrian ramps will be removed, and grading will take place in preparation for the new ramps.

    • Note: This information is general project information. If you have specific questions regarding the impacts to your property, please contact Craig directly. Phasing areas are specified on the construction brochure.

      Questions? Please call Craig Svoboda at 612-490-8748.

      Thank you for your patience!



  • Construction Update for Week of June 1

    Share Construction Update for Week of June 1 on Facebook Share Construction Update for Week of June 1 on X (formerly Twitter) Share Construction Update for Week of June 1 on Linkedin Email Construction Update for Week of June 1 link

    • Saturday, May 30 Crews will be working to prepare subgrade for paving that will take place later in the week.
    • Monday & Tuesday, 6/1-6/2 Crews will wrap up the final grading and compaction work. Excavation of the pond will begin Monday and continue throughout the week.
    • Wednesday (6/3) Crews will begin laying the first lift of fresh asphalt on the following streets: Colorado Ave, Brunswick Ave, Alabama Ave cul-de-sac, Zarthan Ave, 139th St, Yosemite Circle, and Yosemite Court.
    • Thursday, 6/4 Crews will begin laying the first lift of fresh asphalt on the following streets: 140th Street, Alabama Ave, Yosemite Ave and 144th Street.
    • Friday, 6/5 Topsoil placement will begin as part of the restoration of the boulevards.
    • Important Information About Paving Days

      Parking Requirements

      • No street parking allowed on paving days
      • Keep all vehicles in your driveway or park on nearby streets outside the construction zone
    • Access During Paving
      • You'll still be able to get in and out of your driveway throughout the paving process. However, if the paving equipment is working directly in front of your home, you may need to wait 15-30 minutes for the asphalt to cool down before driving over it. Our crew will help coordinate your access and get you in and out as quickly as possible.
      • Safety Reminders Please drive carefully through the construction area. You may need to navigate around equipment, and conditions can change throughout the day.
    • Construction will be moving to Phase 3 and 4 (Preserve Trail) starting mid-week with curb marking and saw cutting work of curb that will be replaced (weather permitting).
    • If you have irrigation damage from construction, please contact Sue with your address @ 952-882-2671 or smeyer@savagemn.gov(External link)(External link)(External link).

    Note: This information is general project information. If you have specific questions regarding the impacts to your property, please contact Craig directly. Phasing areas are specified on the construction brochure.

    Questions? Please call Craig Svoboda at 612-490-8748.

    Thank you for your patience!


    • Saturday, May 30 Crews will be working to prepare subgrade for paving that will take place later in the week.
    • Monday & Tuesday, 6/1-6/2 Crews will wrap up the final grading and compaction work. Excavation of the pond will begin Monday and continue throughout the week.
    • Wednesday (6/3) Crews will begin laying the first lift of fresh asphalt on the following streets: Colorado Ave, Brunswick Ave, Alabama Ave cul-de-sac, Zarthan Ave, 139th St, Yosemite Circle, and Yosemite Court.
    • Thursday, 6/4 Crews will begin laying the first lift of fresh asphalt on the following streets: 140th Street, Alabama Ave, Yosemite Ave and 144th Street.
    • Friday, 6/5 Topsoil placement will begin as part of the restoration of the boulevards.
    • Important Information About Paving Days

      Parking Requirements

      • No street parking allowed on paving days
      • Keep all vehicles in your driveway or park on nearby streets outside the construction zone
    • Access During Paving
      • You'll still be able to get in and out of your driveway throughout the paving process. However, if the paving equipment is working directly in front of your home, you may need to wait 15-30 minutes for the asphalt to cool down before driving over it. Our crew will help coordinate your access and get you in and out as quickly as possible.
      • Safety Reminders Please drive carefully through the construction area. You may need to navigate around equipment, and conditions can change throughout the day.
    • Construction will be moving to Phase 3 and 4 (Preserve Trail) starting mid-week with curb marking and saw cutting work of curb that will be replaced (weather permitting).
    • If you have irrigation damage from construction, please contact Sue with your address @ 952-882-2671 or smeyer@savagemn.gov(External link)(External link)(External link).

    Note: This information is general project information. If you have specific questions regarding the impacts to your property, please contact Craig directly. Phasing areas are specified on the construction brochure.

    Questions? Please call Craig Svoboda at 612-490-8748.

    Thank you for your patience!

  • Construction Update for Week of May 25

    Share Construction Update for Week of May 25 on Facebook Share Construction Update for Week of May 25 on X (formerly Twitter) Share Construction Update for Week of May 25 on Linkedin Email Construction Update for Week of May 25 link
    • Crews will not be working on Monday, May 25 in observance of the Memorial Day Holiday.
    • Pavement removal will begin on Tuesday through Wednesday.
    • After the pavement is removed, crews will work on lowering manholes and gate valves on Wednesday and Thursday.
    • Towards the end of the week (Thursday/Friday), grading / blading will take place to shape the aggregate base.
    • Construction will be moving to Phase 3 and 4 (Preserve Trail) starting June 1 (weather permitting).
    • If you have irrigation damage from construction, please contact Sue with your address @ 952-882-2671 or smeyer@savagemn.gov(External link)(External link).

    Note: This information is general project information. If you have specific questions regarding the impacts to your property, please contact Craig directly. Phasing areas are specified on the construction brochure located to the right under documents.

    Questions? Please call Craig Svoboda at 612-490-8748.

    Thank you for your patience!


    • Crews will not be working on Monday, May 25 in observance of the Memorial Day Holiday.
    • Pavement removal will begin on Tuesday through Wednesday.
    • After the pavement is removed, crews will work on lowering manholes and gate valves on Wednesday and Thursday.
    • Towards the end of the week (Thursday/Friday), grading / blading will take place to shape the aggregate base.
    • Construction will be moving to Phase 3 and 4 (Preserve Trail) starting June 1 (weather permitting).
    • If you have irrigation damage from construction, please contact Sue with your address @ 952-882-2671 or smeyer@savagemn.gov(External link)(External link).

    Note: This information is general project information. If you have specific questions regarding the impacts to your property, please contact Craig directly. Phasing areas are specified on the construction brochure located to the right under documents.

    Questions? Please call Craig Svoboda at 612-490-8748.

    Thank you for your patience!


  • Construction Update for Week of May18

    Share Construction Update for Week of May18 on Facebook Share Construction Update for Week of May18 on X (formerly Twitter) Share Construction Update for Week of May18 on Linkedin Email Construction Update for Week of May18 link
    • Residents affected by the new concrete curb & gutter installation have received a flyer with parking information. Please remember to remove needed vehicles, campers & boats from your driveway before 7:00 a.m. on the day of your installation.
    • Curb & Gutter replacement will be complete by the end of Tuesday, weather permitting.
    • Wednesday, Thursday & Friday are reserved for rain makeup or for finishing up any loose ends regarding concrete work.
    • If you have irrigation damage from construction, please contact Sue with your address @ 952-882-2671 or smeyer@savagemn.gov(External link).

    Note: This information is general project information. If you have specific questions regarding the impacts to your property, please contact Craig directly. Phasing areas are specified on the construction brochure located to the right under documents.

    Questions? Please call Craig Svoboda at 612-490-8748.

    Thank you for your patience!

    • Residents affected by the new concrete curb & gutter installation have received a flyer with parking information. Please remember to remove needed vehicles, campers & boats from your driveway before 7:00 a.m. on the day of your installation.
    • Curb & Gutter replacement will be complete by the end of Tuesday, weather permitting.
    • Wednesday, Thursday & Friday are reserved for rain makeup or for finishing up any loose ends regarding concrete work.
    • If you have irrigation damage from construction, please contact Sue with your address @ 952-882-2671 or smeyer@savagemn.gov(External link).

    Note: This information is general project information. If you have specific questions regarding the impacts to your property, please contact Craig directly. Phasing areas are specified on the construction brochure located to the right under documents.

    Questions? Please call Craig Svoboda at 612-490-8748.

    Thank you for your patience!

Page last updated: 01 Jul 2026, 12:57 PM