Construction Update for the week of 7/6
Phase 3 & 4 (Preserve Trail)
A few more changes for this week:- Wednesday, 7/1: No paving took place due to the weather.
- Thursday, 7/2: Crews will finish paving.
- Friday, 7/3: Holiday. Crews will not be working.
Week of 7/6:
- Crews will be backfilling curbs to get ready for restoration. Sod will be installed mid to the end of the week.
- Irrigation Damage from Construction? Please contact Sue with your address @ 952-882-2671 or smeyer@savagemn.gov(External link)(External link)(External link)(External link)(External link).
- Pond work will begin as soon as the weather dries up and cooperates.
You will still be able to get in and out of your home, but please expect minor delays and please no street parking on paving day. Our crew will help coordinate your access and get you in and out as quickly as possible. The second layer of asphalt will be installed at a later date.
Questions? Please call Craig Svoboda at 612-490-8748.
Thank you!
Share Construction Update for the week of 7/6 on Facebook
Share Construction Update for the week of 7/6 on X (formerly Twitter)
Share Construction Update for the week of 7/6 on Linkedin
Email Construction Update for the week of 7/6 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends