Construction Update for August 21, 24 & 25
Just wanted to communicate a few more things coming up in the days ahead. All work is weather permitting.
Friday, August 21: Crews will be around working on installing riser rings on the manholes and turning up gate valve boxes in preparation for final paving.
Phase 2
Monday, August 24: The final layer of asphalt will be laid in the Yosemite area. There will be no on-street parking from 7:00 a.m. to 5:00 p.m. There will be continued access but expect small delays.
Phase 3 & 4
Tuesday, August 25: The final layer of asphalt will be laid in the Preserve Trail area. There will be no on-street parking from 7:00 a.m. to 5:00 p.m. There will be continued access but expect small delays.
Questions? Please call Craig Svoboda at 612-490-8748.