2025 Street Improvement Project

Share 2025 Street Improvement Project on Facebook Share 2025 Street Improvement Project on Twitter Share 2025 Street Improvement Project on Linkedin Email 2025 Street Improvement Project link

Each year, the City performs maintenance on various segments of the City's road system to maximize the useful life of the pavement. The maintenance treatment can vary from crack sealing, seal coating, or patching up to complete reconstruction depending on the condition of the roadway. In order to determine the appropriate treatment, the City uses a Pavement Management Program (PMP). As part of this program, each street within the City has been surveyed, and its condition rated. Based on this rating, roadways are identified for inclusion in the City's annual Street Improvement Program and shown on the City's 10-Year Street Improvement Plan.

The 2025 Street Improvement Project affects approximately 1.8 miles of roadway. Proposed roadways to be improved are shown on the map below and include Colorado Ave., 139th St., Brunswick Ave., 137th S., Alabama Ave., Zarthan Ave., Zarthan Ct., Yosemite Ave., Xenwood Ave., 136th St., 136th Ln., and 147th St.

See below for ongoing updates for the 2025 Neighborhood Street Project. Please check back periodically.



Each year, the City performs maintenance on various segments of the City's road system to maximize the useful life of the pavement. The maintenance treatment can vary from crack sealing, seal coating, or patching up to complete reconstruction depending on the condition of the roadway. In order to determine the appropriate treatment, the City uses a Pavement Management Program (PMP). As part of this program, each street within the City has been surveyed, and its condition rated. Based on this rating, roadways are identified for inclusion in the City's annual Street Improvement Program and shown on the City's 10-Year Street Improvement Plan.

The 2025 Street Improvement Project affects approximately 1.8 miles of roadway. Proposed roadways to be improved are shown on the map below and include Colorado Ave., 139th St., Brunswick Ave., 137th S., Alabama Ave., Zarthan Ave., Zarthan Ct., Yosemite Ave., Xenwood Ave., 136th St., 136th Ln., and 147th St.

See below for ongoing updates for the 2025 Neighborhood Street Project. Please check back periodically.



  • May 19 - 23, 2025

    Share May 19 - 23, 2025 on Facebook Share May 19 - 23, 2025 on Twitter Share May 19 - 23, 2025 on Linkedin Email May 19 - 23, 2025 link

    Work for next week:

    • Installation of drain tile on 137th Street, Yosemite Avenue, & Xenwood Avenue
    • Concrete curb & gutter replacement on 137th Street, Yosemite Avenue, & Xenwood Avenue, 139th Street and Zarthan. Please park vehicles on the street if more than half of your driveway curb is being replaced. Curing time is typically 7 days but we will let you know if you can access sooner.
  • May 14, 2025

    Share May 14, 2025 on Facebook Share May 14, 2025 on Twitter Share May 14, 2025 on Linkedin Email May 14, 2025 link

    Concrete curb & gutter work expected on 136th Street, 136th Lane, Zarthan Ave & Alabama Ave. Please park vehicles on the street if more than half of your driveway curb is being replaced. Curing time is typically 7 days but we will let you know if you can access sooner.

  • May 12, 2025

    Share May 12, 2025 on Facebook Share May 12, 2025 on Twitter Share May 12, 2025 on Linkedin Email May 12, 2025 link

    Quick Update: Concrete work will be starting Wednesday, May 14 (not today).

  • May 12 - 16, 2025

    Share May 12 - 16, 2025 on Facebook Share May 12 - 16, 2025 on Twitter Share May 12 - 16, 2025 on Linkedin Email May 12 - 16, 2025 link
    • New Storm Sewer installation will take place on Zarthan Ave.
    • Yard Drains and Drain Tile will tentatively be installed on Yosemite, 137th Street, and Xenwood.
    • Concrete Curb & Gutter is expected to start on Monday, 5/12 for Colorado Ave, 139th Street, and Brunswick Ave. Access to driveways may be impacted and street parking will need to be utilized during installation and cure time. Please contact Kale Milek with any questions at 952-292-2221.
    • Concrete work will continue throughout the week. We will do our best to update.
  • May 5 - 9, 2025

    Share May 5 - 9, 2025 on Facebook Share May 5 - 9, 2025 on Twitter Share May 5 - 9, 2025 on Linkedin Email May 5 - 9, 2025 link
    • Storm Sewer installation.
    • Curb & Gutter removal & replacement.
    • Street parking required in areas where new curb was installed to allow concrete to set.
  • April 28, 2025 to May 2, 2025

    Share April 28, 2025 to May 2, 2025 on Facebook Share April 28, 2025 to May 2, 2025 on Twitter Share April 28, 2025 to May 2, 2025 on Linkedin Email April 28, 2025 to May 2, 2025 link
    • Storm sewer installation.
    • Curb and sidewalk removals.


  • April 24, 2025

    Share April 24, 2025 on Facebook Share April 24, 2025 on Twitter Share April 24, 2025 on Linkedin Email April 24, 2025 link

    Temporary Mailbox Bank: Herness Construction will be communicating with residents and installing temporary mailboxes for Friday, April 25. The temporary mail bank will be located on the south of Connelly Parkway, East of Yosemite Ave S. and North of 139th St W. All mail will be delivered at this location with the exception of 147th Street which will have their own mail bank installed at a later date.

  • April 21- 25, 2025

    Share April 21- 25, 2025 on Facebook Share April 21- 25, 2025 on Twitter Share April 21- 25, 2025 on Linkedin Email April 21- 25, 2025 link
    • Gate valve replacement work will continue.
    • Storm Sewer work. Expect some temporary limited access to driveways.
  • Gas Main Break

    Share Gas Main Break on Facebook Share Gas Main Break on Twitter Share Gas Main Break on Linkedin Email Gas Main Break link

    Gas leak due to construction
    CenterPoint Energy is on-site repairing a gas leak caused by construction near Alabama Ave and 137th St. If you smell a strong odor of natural gas in your home, evacuate and call 9-1-1. If you are without service or need additional information, please contact CenterPoint Energy.

  • April 14 - 18, 2025

    Share April 14 - 18, 2025 on Facebook Share April 14 - 18, 2025 on Twitter Share April 14 - 18, 2025 on Linkedin Email April 14 - 18, 2025 link
    • Watermain valve bolt replacement.
    • Storm sewer installation - expect some short-term limited access into driveways during the daytime.
Page last updated: 15 May 2025, 01:38 PM