2025 Street Improvement Project

Share 2025 Street Improvement Project on Facebook Share 2025 Street Improvement Project on Twitter Share 2025 Street Improvement Project on Linkedin Email 2025 Street Improvement Project link

Each year, the City performs maintenance on various segments of the City's road system to maximize the useful life of the pavement. The maintenance treatment can vary from crack sealing, seal coating, or patching up to complete reconstruction depending on the condition of the roadway. In order to determine the appropriate treatment, the City uses a Pavement Management Program (PMP). As part of this program, each street within the City has been surveyed, and its condition rated. Based on this rating, roadways are identified for inclusion in the City's annual Street Improvement Program and shown on the City's 10-Year Street Improvement Plan.

The 2025 Street Improvement Project affects approximately 1.8 miles of roadway. Proposed roadways to be improved are shown on the map below and include Colorado Ave., 139th St., Brunswick Ave., 137th S., Alabama Ave., Zarthan Ave., Zarthan Ct., Yosemite Ave., Xenwood Ave., 136th St., 136th Ln., and 147th St.

See below for ongoing updates for the 2025 Neighborhood Street Project. Please check back periodically.



Each year, the City performs maintenance on various segments of the City's road system to maximize the useful life of the pavement. The maintenance treatment can vary from crack sealing, seal coating, or patching up to complete reconstruction depending on the condition of the roadway. In order to determine the appropriate treatment, the City uses a Pavement Management Program (PMP). As part of this program, each street within the City has been surveyed, and its condition rated. Based on this rating, roadways are identified for inclusion in the City's annual Street Improvement Program and shown on the City's 10-Year Street Improvement Plan.

The 2025 Street Improvement Project affects approximately 1.8 miles of roadway. Proposed roadways to be improved are shown on the map below and include Colorado Ave., 139th St., Brunswick Ave., 137th S., Alabama Ave., Zarthan Ave., Zarthan Ct., Yosemite Ave., Xenwood Ave., 136th St., 136th Ln., and 147th St.

See below for ongoing updates for the 2025 Neighborhood Street Project. Please check back periodically.



  • July 17 - 25

    Share July 17 - 25 on Facebook Share July 17 - 25 on Twitter Share July 17 - 25 on Linkedin Email July 17 - 25 link

    July 17 - 18

    • Notices were sent out on Monday regarding reinstalling your mailboxes. Crews will be working on reinstalling all permanent mailboxes and removing the temporary mailboxes. Once all mailboxes are back up, mail will resume as normal. Our crews will notify you if they have any issues with your installation.
    • Crews will be on-site though out the project to pave full length driveways.

    July 21 - 25

    • Crews will be removing marked driveway ends though out the project and will work on paving them until finished.

    Access During Driveway Paving: If the paving equipment is working directly in front of your home, you may need to wait 15 - 30 minutes for the asphalt to cool down before driving over it.

    If you have any questions, contact Kale at 952-252-2221.

  • Construction Update July 10.

    Share Construction Update July 10. on Facebook Share Construction Update July 10. on Twitter Share Construction Update July 10. on Linkedin Email Construction Update July 10. link

    Unfortunately, paving had to be postponed today due to the rain. Paving should resume on Friday and will include Alabama Avenue, Xenwood Avenue, 137th Street E, Yosemite Avenue and 147th Street. We anticipate paving to be completed by the end of the day on Friday.

    Access During Paving: You'll still be able to get in and out of your driveway throughout the paving process. However, if the paving equipment is working directly in front of your home, you may need to wait 15 - 30 minutes for the asphalt to cool down before driving over it. Our crew will help coordinate your access and get you in and out as quickly as possible.

    Safety Reminders: Please drive carefully through the construction area. You may need to navigate around equipment, and conditions can change throughout the day.

    Questions: Contact Kale at 612-292-2221 with any questions or concerns about the project.

  • July 8, 2025

    Share July 8, 2025 on Facebook Share July 8, 2025 on Twitter Share July 8, 2025 on Linkedin Email July 8, 2025 link

    Xcel Energy / Michels Pipeline is currently working within the project area replacing faulty underground power lines. This work is outside of the road construction project work scope. If you have any questions, regarding this particular work, please contact Bridget with Xcel Energy at 651-229-5555. Thank you.

  • July 7 - 10, 2025

    Share July 7 - 10, 2025 on Facebook Share July 7 - 10, 2025 on Twitter Share July 7 - 10, 2025 on Linkedin Email July 7 - 10, 2025 link
    • Monday, July 7: Finish grading and compaction and crews continuing to raise utility castings within the street section throughout the site.
    • Tuesday, July 8: Finish raising utility castings within the street section throughout the site.
    • Wednesday & Thursday, July 9 & 10: Paving will begin on Alabama, 136th St, Zarthan, 136th Ln, Brunswick, 139th (west), Colorado, 137th (west). No street parking during paving.

    Things to know for Paving: No Street Parking allowed, please keep vehicles in driveways or parked on another street off-site. Everyone should have access in and out of driveways and throughout the site during paving. If the operation is in front of your house and you need to enter or leave your driveway, you may need to wait until the paver and roller has passed through (15 to 30 minutes for cool down). This will be situational, and we will get you in and out as promptly as possible. Please be cautious while driving around the site as you may need to drive around equipment.

    Please call Kale at 612-292-2221 with any questions.

  • June 30, 2025

    Share June 30, 2025 on Facebook Share June 30, 2025 on Twitter Share June 30, 2025 on Linkedin Email June 30, 2025 link

    Due to weather, there will be no paving on Wednesday, July 2. More updates will be coming as we learn more.

    Thank you.

  • June 30 - July 4, 2025

    Share June 30 - July 4, 2025 on Facebook Share June 30 - July 4, 2025 on Twitter Share June 30 - July 4, 2025 on Linkedin Email June 30 - July 4, 2025 link
    • Monday, June 30 - installing concrete curb & gutter on 147th street. If we are pouring across your driveway entrance, please park on the street.
    • Monday, June 30 & Tuesday, July 1 - Raising utility castings within the street
    • Wednesday, July 2 - Paving Alabama, 136th St, Zarthan, 136th Ln, Brunswick, 139th (west), Colorado, 137th (west). No street parking during paving.
    • No work on Thursday & Friday.

    All weather permitting. Please call Kale at 952-292-2221 with any questions or concerns. Have a great holiday week.

  • June 16 - 24, 2025

    Share June 16 - 24, 2025 on Facebook Share June 16 - 24, 2025 on Twitter Share June 16 - 24, 2025 on Linkedin Email June 16 - 24, 2025 link
    • Grading and tolerancing of the project’s roadway will begin on Monday, 6/16 and will continue through the rest of the week. No street parking during the week as the grading operator will need to blade the road base the full width of each lane.

    • Utility work will continue on Yosemite Ave Monday, 6/16 and will mobilize to 147th Street to begin Storm Sewer work on 147th Street Tuesday and Wednesday, 6/17 & 6/18. Residents will have access to driveways at times, but street parking will be available on Hampshire Ave outside of the project area.
    • Remaining concrete (Curb & Gutter, driveways, sidewalk, etc.), will start on Friday, 6/20 and continue through the following Tuesday, 6/24.

    The schedule is continuously changing due to weather and the activities mentioned for the weeks ahead are all weather permitting.

    Thank you for your patience and understanding. Please contact Kale @ 952-292-2221 with any questions or concerns.

  • 147th Street Update

    Share 147th Street Update on Facebook Share 147th Street Update on Twitter Share 147th Street Update on Linkedin Email 147th Street Update link
    UPDATE for 147th Street - Utility work, storm sewer/drain tile work and milling/reclaiming process will begin on Wednesday, June 11. (not today as originally planned).

    09 Jun 2025
    • The few residents who did not have the curb poured in front of the driveway or property will be completed either 6/12-6/13 or 6/16, weather permitting and coordination between other crews’ completion. All final concrete items for the project will be completed during this time.

    • Complete Milling/reclaim process on 6/9. No street parking during this time for large equipment to navigate through the site.

    • Utility crew to return on 6/9 to complete drain tile and yard drain installation on Yosemite, Xenwood, and 137th street. Storm sewer/drain tile work will also begin on 147th Street. Should be complete by the end of the week, weather permitting.

    • Sub cutting and street preparation on Alabama Ave (Brunswick to 135th street and north loop of 136th St, Zarthan, and 136th Lane to start 6/9-6/10). No street parking during this time and access may be impacted. Navigating through these streets may also be difficult during this operation. This is a 2 or 3-day process weather permitting.

    Things may change but this is the schedule as of now.

    Contact Kale @ 952-292-2221 with questions.

    Thank you!

  • June 9 - 13, 2025

    Share June 9 - 13, 2025 on Facebook Share June 9 - 13, 2025 on Twitter Share June 9 - 13, 2025 on Linkedin Email June 9 - 13, 2025 link
    • The few residents who did not have the curb poured in front of the driveway or property will be completed either 6/12-6/13 or 6/16, weather permitting and coordination between other crews’ completion. All final concrete items for the project will be completed during this time.

    • Complete Milling/reclaim process on 6/9. No street parking during this time for large equipment to navigate through the site.

    • Utility crew to return on 6/9 to complete drain tile and yard drain installation on Yosemite, Xenwood, and 137th street. Storm sewer/drain tile work will also begin on 147th Street. Should be complete by the end of the week, weather permitting.

    • Sub cutting and street preparation on Alabama Ave (Brunswick to 135th street and north loop of 136th St, Zarthan, and 136th Lane to start 6/9-6/10). No street parking during this time and access may be impacted. Navigating through these streets may also be difficult during this operation. This is a 2 or 3-day process weather permitting.

    Things may change but this is the schedule as of now.

    Contact Kale @ 952-292-2221 with questions.

    Thank you!

  • June 9 - 13, 2025

    Share June 9 - 13, 2025 on Facebook Share June 9 - 13, 2025 on Twitter Share June 9 - 13, 2025 on Linkedin Email June 9 - 13, 2025 link

    Please disregard the most recent update that was sent out this morning. It was sent out in error.


    My apologies.

Page last updated: 17 Jul 2025, 08:52 AM