August 15 - 22, 2025

Here are the updates for the upcoming week!

    • Crews will be finishing up sod today and will work part of Saturday, 8/16, if needed.
    • Disturbed landscaping items will be taken care of late in the week or the following.
    • Most of the irrigation systems have been repaired. If anything needs to be revisited, please let us know asap.
    • Remaining concrete work/repairs and asphalt patching repairs will occur all week.
    • NOTE: Wear Course Paving is expected to be completed the week of 8/25.We will notify you when a specific day is set. Paving notes to prepare for:
      • No Street Parking allowed, please keep vehicles in driveways or parked on another street off-site. Everyone should have access in and out of driveways and throughout the site during paving, but delays should be expected if the operation is in front of your house and you need to enter or leave your driveway. You may need to wait until the paver and roller has passed through (15 to 30 minutes for cool down). Please be mindful that there will also be a tack coat placed prior to the paver making a pass. Be cautious of the tack coat as it is very sticky and shouldn't be driven on. The tack coat takes about 30 minutes to setup.
    • No street Parking
    • Residents can use parks or other streets outside of the project for parking if needing to leave during the day.

Questions? Please call Kale at 952-292-2221.

Thank you.

Share August 15 - 22, 2025 on Facebook Share August 15 - 22, 2025 on Twitter Share August 15 - 22, 2025 on Linkedin Email August 15 - 22, 2025 link