July 7 - 10, 2025
- Monday, July 7: Finish grading and compaction and crews continuing to raise utility castings within the street section throughout the site.
- Tuesday, July 8: Finish raising utility castings within the street section throughout the site.
- Wednesday & Thursday, July 9 & 10: Paving will begin on Alabama, 136th St, Zarthan, 136th Ln, Brunswick, 139th (west), Colorado, 137th (west). No street parking during paving.
Things to know for Paving: No Street Parking allowed, please keep vehicles in driveways or parked on another street off-site. Everyone should have access in and out of driveways and throughout the site during paving. If the operation is in front of your house and you need to enter or leave your driveway, you may need to wait until the paver and roller has passed through (15 to 30 minutes for cool down). This will be situational, and we will get you in and out as promptly as possible. Please be cautious while driving around the site as you may need to drive around equipment.
Please call Kale at 612-292-2221 with any questions.
Share July 7 - 10, 2025 on Facebook
Share July 7 - 10, 2025 on Twitter
Share July 7 - 10, 2025 on Linkedin
Email July 7 - 10, 2025 link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends