Construction Update Week of May 11
Thank you for signing up on Let's Talk Savage for updates on the 2026 Street Improvement Project in your neighborhood.
Week of May 11, 2026
-
Phase 1:
- New Storm Sewer installation will begin on Alabama Avenue, Zarthan Avenue & 140th Street.
- Crews will finish removing concrete sidewalk panels on Monday & Tuesday. Finish removing curb & gutter that has been marked for removal.
- Later in the week, new concrete pedestrian ramps will begin.
- At the end of the week, new concrete curb & gutter will be installed. Please watch for informational flyers on your door regarding this activity.
-
Phase 2:
- Crews will be replacing bolts on the gate valves that are part of the water main. They will be working on Yosemite Avenue, 139th Street, Yosemite Circle & Court, & 141st Street.
-
Phase 1 & 2:
- Please continue getting your mail in the temporary mailboxes located on Connelly Parkway.
- Expect some heavy equipment and trenching which may cause minor delays.
- If you have irrigation damage from construction, please contact Sue with your address @ 952-882-2671 or smeyer@savagemn.gov.
Note: This information is general project information. If you have specific questions regarding the impacts to your property, please contact Craig directly. Phasing areas are specified on the construction brochure located to the right under documents.
Questions? Please call Craig Svoboda at 612-490-8748.
Thank you for your patience!
Share Construction Update Week of May 11 on Facebook
Share Construction Update Week of May 11 on Twitter
Share Construction Update Week of May 11 on Linkedin
Email Construction Update Week of May 11 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends