Construction Update Week of June 8
Phase 1 & 2
- All week: Restoration crews will start placing topsoil in boulevards in preparation for sod. Sod to follow soon! Watch for a mailing to be sent soon after sod is placed regarding sod care and warranty information.
-
Wednesday - Friday: Pond excavation work will begin.
-
If you have irrigation damage from construction, please contact Sue with your address @ 952-882-2671 or smeyer@savagemn.gov(External link)(External link)(External link)(External link).
Phase 3 & 4 (Preserve Trail)
- Utility work will begin.
- Marked curb will be removed.
- Old pedestrian ramps will be removed, and grading will take place in preparation for the new ramps.
-
Note: This information is general project information. If you have specific questions regarding the impacts to your property, please contact Craig directly. Phasing areas are specified on the construction brochure.
Questions? Please call Craig Svoboda at 612-490-8748.
Thank you for your patience!
Share Construction Update Week of June 8 on Facebook
Share Construction Update Week of June 8 on Twitter
Share Construction Update Week of June 8 on Linkedin
Email Construction Update Week of June 8 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends