Construction Update for Week of May 25
- Crews will not be working on Monday, May 25 in observance of the Memorial Day Holiday.
- Pavement removal will begin on Tuesday through Wednesday.
- After the pavement is removed, crews will work on lowering manholes and gate valves on Wednesday and Thursday.
- Towards the end of the week (Thursday/Friday), grading / blading will take place to shape the aggregate base.
- Construction will be moving to Phase 3 and 4 (Preserve Trail) starting June 1 (weather permitting).
- If you have irrigation damage from construction, please contact Sue with your address @ 952-882-2671 or smeyer@savagemn.gov(External link)(External link).
Note: This information is general project information. If you have specific questions regarding the impacts to your property, please contact Craig directly. Phasing areas are specified on the construction brochure located to the right under documents.
Questions? Please call Craig Svoboda at 612-490-8748.
Thank you for your patience!
Share Construction Update for Week of May 25 on Facebook
Share Construction Update for Week of May 25 on Twitter
Share Construction Update for Week of May 25 on Linkedin
Email Construction Update for Week of May 25 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends