Construction Update for Week of June 1
- Saturday, May 30 Crews will be working to prepare subgrade for paving that will take place later in the week.
- Monday & Tuesday, 6/1-6/2 Crews will wrap up the final grading and compaction work. Excavation of the pond will begin Monday and continue throughout the week.
- Wednesday (6/3) Crews will begin laying the first lift of fresh asphalt on the following streets: Colorado Ave, Brunswick Ave, Alabama Ave cul-de-sac, Zarthan Ave, 139th St, Yosemite Circle, and Yosemite Court.
- Thursday, 6/4 Crews will begin laying the first lift of fresh asphalt on the following streets: 140th Street, Alabama Ave, Yosemite Ave and 144th Street.
- Friday, 6/5 Topsoil placement will begin as part of the restoration of the boulevards.
-
Important Information About Paving Days
Parking Requirements
- No street parking allowed on paving days
- Keep all vehicles in your driveway or park on nearby streets outside the construction zone
-
Access During Paving
- You'll still be able to get in and out of your driveway throughout the paving process. However, if the paving equipment is working directly in front of your home, you may need to wait 15-30 minutes for the asphalt to cool down before driving over it. Our crew will help coordinate your access and get you in and out as quickly as possible.
- Safety Reminders Please drive carefully through the construction area. You may need to navigate around equipment, and conditions can change throughout the day.
- Construction will be moving to Phase 3 and 4 (Preserve Trail) starting mid-week with curb marking and saw cutting work of curb that will be replaced (weather permitting).
- If you have irrigation damage from construction, please contact Sue with your address @ 952-882-2671 or smeyer@savagemn.gov(External link)(External link)(External link).
Note: This information is general project information. If you have specific questions regarding the impacts to your property, please contact Craig directly. Phasing areas are specified on the construction brochure.
Questions? Please call Craig Svoboda at 612-490-8748.
Thank you for your patience!
Share Construction Update for Week of June 1 on Facebook
Share Construction Update for Week of June 1 on Twitter
Share Construction Update for Week of June 1 on Linkedin
Email Construction Update for Week of June 1 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends