May 19 - 23, 2025
Work for next week:
- Installation of drain tile on 137th Street, Yosemite Avenue, & Xenwood Avenue
- Concrete curb & gutter replacement on 137th Street, Yosemite Avenue, & Xenwood Avenue, 139th Street and Zarthan. Please park vehicles on the street if more than half of your driveway curb is being replaced. Curing time is typically 7 days but we will let you know if you can access sooner.