May 14, 2025

Concrete curb & gutter work expected on 136th Street, 136th Lane, Zarthan Ave & Alabama Ave. Please park vehicles on the street if more than half of your driveway curb is being replaced. Curing time is typically 7 days but we will let you know if you can access sooner.