June 9 - 13, 2025
- The few residents who did not have the curb poured in front of the driveway or property will be completed either 6/12-6/13 or 6/16, weather permitting and coordination between other crews’ completion. All final concrete items for the project will be completed during this time.
- Complete Milling/reclaim process on 6/9. No street parking during this time for large equipment to navigate through the site.
- Utility crew to return on 6/9 to complete drain tile and yard drain installation on Yosemite, Xenwood, and 137th street. Storm sewer/drain tile work will also begin on 147th Street. Should be complete by the end of the week, weather permitting.
- Sub cutting and street preparation on Alabama Ave (Brunswick to 135th street and north loop of 136th St, Zarthan, and 136th Lane to start 6/9-6/10). No street parking during this time and access may be impacted. Navigating through these streets may also be difficult during this operation. This is a 2 or 3-day process weather permitting.
Things may change but this is the schedule as of now.
Contact Kale @ 952-292-2221 with questions.
Thank you!
Share June 9 - 13, 2025 on Facebook
Share June 9 - 13, 2025 on Twitter
Share June 9 - 13, 2025 on Linkedin
Email June 9 - 13, 2025 link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends