  • Monday, June 30 - installing concrete curb & gutter on 147th street. If we are pouring across your driveway entrance, please park on the street.
  • Monday, June 30 & Tuesday, July 1 - Raising utility castings within the street
  • Wednesday, July 2 - Paving Alabama, 136th St, Zarthan, 136th Ln, Brunswick, 139th (west), Colorado, 137th (west). No street parking during paving.
  • No work on Thursday & Friday.

All weather permitting. Please call Kale at 952-292-2221 with any questions or concerns. Have a great holiday week.