June 2 - June 6, 2025

  • All remaining driveways where curb & gutter was poured will have driveway access Monday/Tuesday 6/2 & 6/3.

  • The few residents who did not have the curb poured in front of the driveway or property will be completed either 6/12-6/13 or 6/16, weather permitting and coordination between other crews’ completion. All final concrete items for the project will be completed during this time.

  • Milling/reclaim process will begin on 6/4 to be completed 6/6 weather permitting. No street parking during this time for large equipment to navigate through the site.

  • Utility crew to return on 6/9 to complete drain tile and yard drain installation on Yosemite, Xenwood, and 137th street. Storm sewer/drain tile work will also begin on 147th Street.

  • Sub cutting and street preparation on Alabama Ave (Brunswick to 135th street and north loop of 136th St, Zarthan, and 136th Lane to start 6/9-6/10). No street parking during this time and access may be impacted. Navigating through these streets may also be difficult during this operation. 2 or 3-day process weather permitting.

Things will change but this is the tentative schedule as of now.

Contact Kale @ 952-292-2221 with questions.

Thank you!