June 16 - 24, 2025
- Grading and tolerancing of the project’s roadway will begin on Monday, 6/16 and will continue through the rest of the week. No street parking during the week as the grading operator will need to blade the road base the full width of each lane.
- Utility work will continue on Yosemite Ave Monday, 6/16 and will mobilize to 147th Street to begin Storm Sewer work on 147th Street Tuesday and Wednesday, 6/17 & 6/18. Residents will have access to driveways at times, but street parking will be available on Hampshire Ave outside of the project area.
- Remaining concrete (Curb & Gutter, driveways, sidewalk, etc.), will start on Friday, 6/20 and continue through the following Tuesday, 6/24.
The schedule is continuously changing due to weather and the activities mentioned for the weeks ahead are all weather permitting.
Thank you for your patience and understanding. Please contact Kale @ 952-292-2221 with any questions or concerns.
Share June 16 - 24, 2025 on Facebook
Share June 16 - 24, 2025 on Twitter
Share June 16 - 24, 2025 on Linkedin
Email June 16 - 24, 2025 link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends