Friday, May 23 & Monday, 5/26 - Friday, 5/30

We are doing our best to keep residents updated, but things can change fast. Thank you for your patience and understanding. Here is the latest update:

Friday, May 23

  • Curb & Gutter placement on all of 139th Street and portions of 137th Street.

Monday, May 26 - Friday, May 30

  • Monday - No Work - Holiday
  • Tuesday - Friday - Curb & Gutter placement on Yosemite, Xenwood Ave, 137th Street & Zarthan.

Please contact Kale Milek @ 952-292-2221 with any questions or concerns.