August 26 - September 5, 2025

Construction Update August 26 - September 5, 2025

  • The remaining concrete curb & gutter will be poured by the end of this week.
  • Paving of the road has been moved to next week. Crews will not be working on September 1 due to the Labor Day Holiday.
  • Please verify that your irrigation systems are working properly after repairs were made. If it is not working properly, please contact Kale as soon as possible.

Questions? Please call Kale at 952-292-2221.